Da Nang's World Bank-funded Adaptive Integrated Development Project, a 2,723 billion dong scheme of six new bridges, river dredging and flood drainage, has begun construction on several bridges.
According to the Da Nang city portal, the project was originally planned for Quảng Nam province, which now forms part of Da Nang. It covers eight communes and wards in the southeast of the city.
Its three components are six new bridges and one community bridge across the Trường Giang River, dredging of the river route, and a flood-drainage complex in Tam Kỳ. The drainage works include the A3 canal, linking the Đầm River lake to the Trường Giang over about 2.38 kilometres.
The project is classed as Category A and funded by official development assistance. The World Bank contributes about 1,838.5 billion dong (US$76.57 million), with about 884.2 billion dong (US$36.82 million) in counterpart funds.
By the reporting date it had disbursed more than 253 billion dong, or 88.8% of its 2026 allocation. The 2027 allocation is 677 billion dong.
Bình Dương Bridge in Thăng An commune broke ground in May. Steel bridge repairs are complete, 11 of 30 Super-T girders have been cast and 19 of 37 bored piles are finished at one abutment and pier.
Tỉnh Thủy Bridge broke ground in June, with 8 of 56 bored piles done. Bình Nam Bridge in Thăng Trường commune started in October, and the contract for Hưng Mỹ Bridge was awarded in November.
Groundbreaking for Tam Tiến Bridge and the community bridge is expected in December. Tam Thanh Bridge is being adjusted, with a start expected in February 2027.
Two dredging packages on the Trường Giang, covering Km0–Km30 and Km30–Km60, are in contractor selection, with work expected in the first quarter of 2027. The channel is to be 30 metres wide and 2.3 metres deep, suited to 100-tonne vessels.
Land clearance is the main hurdle. The 31-kilometre section through Thăng An and Thăng Trường affects 931 land plots, and in Bàn Thạch and Quảng Phú only 1.4 km of an 8.5 km channel has been handed over.
Nguyễn Minh Nam of the city's Land Development Fund Center said agencies aim to finish site clearance before December 2027. Deputy Chairman Trần Nam Hưng asked the project board to resolve problems on five contract packages not yet tendered and to prepare livelihood support for affected residents.
A World Bank disaster-risk expert, Nguyễn Huy Dũng, called the early progress very positive, noting it is rare for a project to move so quickly through bidding and construction after financing takes effect.
Sources
This story was compiled by the Da Nang Voice news desk from the published sources listed above. Facts, figures and quotes are attributed to those sources; Da Nang Voice did not conduct interviews for it unless the text says so. Corrections are dated and noted at the top of the story. Read our corrections policy. Spotted an error? Tell us.