Da Nang has approved the investment policy for a road of about 2.986 km, including a bridge, linking route ĐH5.ĐL with provincial road ĐT.609C through Phú Thuận and Vu Gia communes. The decision, No. 5262/QĐ-UBND, was listed in the city government's summary of directives for 17 November.

Total investment is about 340 billion dong. The project is split into two independent components.

Component 1, site clearance, is budgeted at 49.6 billion dong and owned by the Da Nang Land Fund Development Centre. Component 2, construction, is budgeted at 290.3 billion dong and owned by the Da Nang management board for transport and agricultural construction projects.

The project timeline is 2026 to 2029. The summary gave no start date for construction.

Sources

This story was compiled by the Da Nang Voice news desk from the published sources listed above. Facts, figures and quotes are attributed to those sources; Da Nang Voice did not conduct interviews for it unless the text says so. Corrections are dated and noted at the top of the story. Read our corrections policy. Spotted an error? Tell us.