Three beachfront projects on Da Nang's Truong Sa coastal road have sat idle for years, and a Tuoi Tre investigation published on 13 November sets out why. The sites, known as DAP, DAP1 and DAP2 and located in Hoa Hai ward, cover only about 15 hectares in total, and weeds now grow inside them, Tuoi Tre reports.

The paper traces the problem to the way the land was handled from the start. The city and the Dubai company, which originally held the projects, signed an agreement in principle in April 2007. Investment certificates followed that year, and three land lease contracts and land use certificates were issued in 2008.

According to inspection findings cited by Tuoi Tre, several incentives granted at the time did not follow regulations. These include a three-year land rent exemption and a 30% rent reduction for projects that were not in eligible sectors or areas. The inspectors also found that land rent was set without a valuation method or the city valuation council's proposal, and that land was allocated without an auction or bidding.

Planning created a second problem. A 2015 revision of the detailed plan allowed a 20-storey apartment and commercial complex at DAP Viet Nam, on land that the 2013 citywide plan had designated for tourism. The inspection concluded this conflicted with the Urban Planning Law, and that the financial obligations created by the change were never calculated.

Compensation is also unfinished. Seven land files have not been paid since 2015, which Tuoi Tre attributes to slow coordination by the city's Land Development Center. A launch ceremony for the DAP coastal tourism project was held in 2020, but the paper says work has not progressed since.

The city inspectorate found that a large share of the responsibility lies with state management agencies, according to the report. The Department of Agriculture and Environment has hired a consultant to determine land rent, which will set what the projects owe.

The three projects are on the city's list for special mechanisms under National Assembly Resolutions 170 and 29, which are meant to unblock stalled projects. The inspection conclusion said the project "has grounds to apply special mechanisms and policies." DAP, DAP1 and DAP2 were already named among Da Nang projects to be unblocked under the National Assembly's resolution in a VietnamFinance review from February 2025.

Danang Voice could not independently verify the inspection findings, and the report does not include a response from the companies.

Sources

This story was compiled by the Da Nang Voice news desk from the published sources listed above. Facts, figures and quotes are attributed to those sources; Da Nang Voice did not conduct interviews for it unless the text says so. Corrections are dated and noted at the top of the story. Read our corrections policy. Spotted an error? Tell us.