Express delivery companies say moving international express cargo from Tan Son Nhat to Long Thanh airport from the summer 2027 flight season is not feasible, and have asked the Ministry of Construction to delay the move until the necessary infrastructure is finished. The request comes from CAPEC, the Association of International Express Delivery Companies in Vietnam, whose members include DHL-VNPT, FedEx Express Vietnam and UPS Vietnam, according to Dan Tri.
CAPEC described the plan as not feasible technically, operationally or legally. It said no dedicated express cargo warehouse has yet been built at Long Thanh, and that road links between the airport and Ho Chi Minh City, Dong Nai and the main trade areas are incomplete. It also noted that early on, passenger flights may be split between Long Thanh and Tan Son Nhat, which would make transferring cargo between the two airports difficult without good road connections.
The association said the general cargo terminal being developed by Airports Corporation of Vietnam (ACV), expected to open at the end of 2026, does not meet the specialised needs of express delivery and is not designated for inspecting or clearing express goods through customs.
By CAPEC's preliminary assessment, international express firms need about 12 months to prepare and complete technical evaluations. The investor needs at least 12 to 18 months to build the warehouse and basic facilities, and the express companies then need another 12 months to fit out facilities, install equipment and set up dedicated systems. The report added that, according to the Ministry of Construction, package 7.8, covering cargo terminal No. 1 and auxiliary works, is among four packages that may not be fully finished in December.
ACV's proposed schedule would move all long-haul international flights, including cargo, to Long Thanh for the summer 2027 season, which runs from March to October 2027. A survey by the Civil Aviation Authority of Vietnam found that 24 international airlines want to move from the winter 2027 season, while 10 want to move from summer 2028 or later.
CAPEC asked that cargo and express flights, including those of UPS Airlines, FedEx Airlines and Air Hong Kong, move only once essential infrastructure is complete. It also asked that warehouses and express facilities be finished several months beforehand so companies can import equipment and hire and train staff.
The association warned that a premature move could lengthen transit and customs times, raise logistics costs and reduce service quality. The report did not include a response from the Ministry of Construction or ACV to the request.
Sources
This story was compiled by the Da Nang Voice news desk from the published sources listed above. Facts, figures and quotes are attributed to those sources; Da Nang Voice did not conduct interviews for it unless the text says so. Corrections are dated and noted at the top of the story. Read our corrections policy. Spotted an error? Tell us.