Da Nang's People's Committee has approved the investment policy and the investor for a project on plot 6 of the Da Nang Free Trade Zone, Báo Đà Nẵng reported on October 13, 2026. The paper cites Decision 4684/QĐ-UBND.
The investor is FTZ KITA Trung Nam Co., Ltd, based at Indochina Riverside Tower on Bạch Đằng Street. The project is to build and operate infrastructure for a functional zone of about 154 hectares, which the report places in Bà Nà commune. Its proposed trade name is International Commercial & Service Gateway.
Total capital is about 3,354.8 billion dong. The investor puts in 800 billion dong, or 23.85%, which the report says is fully paid in. The remaining 2,554 billion dong or so is to come from credit institutions and other lawful sources.
The report gives this schedule:
- 2026: approvals, planning, surveys and site clearance, including forestry land procedures.
- 2027: continued clearance and the first infrastructure on eligible land.
- 2028: land leveling, roads and main technical infrastructure.
- Fourth quarter of 2029: target for completion and operation, while seeking secondary investors.
- 2030: final settlement of construction items.
The project term is 70 years from the date the State decides on the land lease. The report adds that the project may qualify for a full land-rent exemption for the whole term under two National Assembly resolutions; that is described as under consideration, not granted.
Why it matters: Approval of the investor is a first step. The land lease decision, forest land procedures and the borrowing for more than two-thirds of the capital are all still ahead, and the report does not say who the secondary investors might be.
Sources
This story was compiled by the Da Nang Voice news desk from the published sources listed above. Facts, figures and quotes are attributed to those sources; Da Nang Voice did not conduct interviews for it unless the text says so. Corrections are dated and noted at the top of the story. Read our corrections policy. Spotted an error? Tell us.