Gia Lai province has launched a 40-day campaign, running from 20 November to 29 December 2026, to speed up housing and resettlement projects for people living in disaster-prone areas.

According to Tien Phong, the provincial People's Committee announced the campaign on 23 November. It covers 16 projects and plans to relocate and stabilise residents.

Progress so far is uneven. Compensation for old homes has been approved for 895 of 1,351 households, leaving 456 households still waiting.

On construction, work has started on 676 of the 1,225 houses in the 2026 plan. That leaves 549 houses not yet begun.

The report names the slowest localities as Uar, Cat Tien, Phu My Dong, An Hoa and Phu My Bac. Officials want construction started on every house in the 2026 plan before 30 November.

Households that already have livable homes are to be relocated before 25 December, with the highest-risk areas given priority. Other resettlement areas must finish their infrastructure before 31 December 2026.

At the Mỹ Thắng resettlement area in Phu My Dong commune, the target is to be substantially complete before 30 November. Roads, electricity and water supply come first, and Tien Phong says work continues in three shifts with four crews, including rest days.

Responsibility is placed directly on local leaders. Party secretaries and chairpersons of communes and wards are accountable for progress and results.

Investors and communes have also been told to finish payment paperwork and disburse funds promptly. They must report the reasons if money cannot be fully disbursed.

The report does not give a total budget for the campaign. A separate Tien Phong headline mentions about VND407 billion for emergency relocation of 290 households, but that figure is not part of this report.

The article describes the push as a race against time. Officials want people moved into safe homes before the end of the year, after a season in which central and highland provinces faced repeated floods and landslides.

Two figures show how much remains to be done. More than half of the houses in the 2026 plan have not yet started construction, and a third of the compensation cases are still unapproved.

Sources

This story was compiled by the Da Nang Voice news desk from the published sources listed above. Facts, figures and quotes are attributed to those sources; Da Nang Voice did not conduct interviews for it unless the text says so. Corrections are dated and noted at the top of the story. Read our corrections policy. Spotted an error? Tell us.