Traffic on the HCMC-Long Thanh expressway will move onto newly built widening lanes from 00:00 on November 22, Dan Tri reported on November 20, citing the Vietnam Expressway Corporation (VEC). The switch lets the contractor start upgrading the existing roadbed.

The new lanes run from Long Thanh Bridge in An Phuoc commune to the National Highway 51 interchange in Long Thanh ward, from Km14+000 to Km23+900. VEC said the authorities had inspected and approved opening that section.

The stretch from the Highway 51 interchange to the Bien Hoa-Vung Tau expressway interchange is still under construction and is due to finish in December. VEC aims to complete all of Package No. 2 before December 24, the date Long Thanh Airport is expected to begin commercial operation.

The project covers nearly 22 kilometres in two packages, widening the road from four lanes to eight or ten. VEC put overall progress at 81.5 percent: 81.23 percent for Package No. 1 and 81.83 percent for Package No. 2.

Package No. 1 is targeting elevated bridge work in December, operation from January 2027 and full completion in the first quarter of 2027. Package No. 2 is targeting its main items in December and full operation in January 2027.

VEC asked drivers to follow temporary signs and road markings, respect speed limits and obey traffic officers.

Sources

This story was compiled by the Da Nang Voice news desk from the published sources listed above. Facts, figures and quotes are attributed to those sources; Da Nang Voice did not conduct interviews for it unless the text says so. Corrections are dated and noted at the top of the story. Read our corrections policy. Spotted an error? Tell us.