Ho Chi Minh City plans to pay for a roughly 42-kilometre expressway to Long Thành airport and Hồ Tràm mainly with city land, VnExpress reported on 18 November. The city's Department of Finance has submitted the proposal to the municipal People's Committee for approval.

The Hồ Tràm–Long Thành International Airport urban expressway would be built under a build-transfer (BT) contract, which is expected to be signed in December 2026. Construction is planned for 2026–2029 and the contract runs from 2026 to 2032. Long Thành airport is expected to open on 24 December.

The project has two parts. The first is a roughly 2.27-kilometre interchange linking provincial road ĐT.991 with HCMC Ring Road 4, costing 2,384 billion dong, which the city approved in June. The second is almost 40 kilometres from the upper interchange to the ĐT.994 interchange in Xuyên Mộc commune, costing more than 38,400 billion dong, including over 12,500 billion for compensation and resettlement on about 396 hectares.

Total investment is about 40,828 billion dong. The investor, Masterise Hạ tầng cao tốc Long Thành – Hồ Tràm JSC, would raise all the capital itself, 15 percent equity and 85 percent loans and other lawful sources.

The six-lane road would have a 100 km/h limit and frontage roads on both sides. About 5.7 kilometres would be elevated through the Bình Châu–Phước Bửu conservation area to limit forest impact, with bridges over Suối Rao lake (about 890 metres) and Sông Ray 2 lake (nearly 1.5 kilometres).

In payment, the city would hand over seven plots totalling about 179 hectares, valued at about 34,930.85 billion dong. The remaining value, nearly 5,900 billion dong, would come from the budget within three years after the road is accepted and opened.

The two largest plots, the 40-hectare Trường Thọ urban area in Thủ Đức ward (16,775 billion dong) and the Nông trường Dừa site in Long Trường ward (13,999 billion), make up more than 88 percent of the value. The other five are central-city sites on Hàm Nghi, Trần Hưng Đạo, Võ Văn Tần, Lê Văn Duyệt and Nơ Trang Long streets. The land would be transferred in one lump sum after the contract is signed.

The plan is a proposal and still needs approval from the city People's Committee.

Sources

This story was compiled by the Da Nang Voice news desk from the published sources listed above. Facts, figures and quotes are attributed to those sources; Da Nang Voice did not conduct interviews for it unless the text says so. Corrections are dated and noted at the top of the story. Read our corrections policy. Spotted an error? Tell us.