Thirty-four international airlines have asked to postpone moving their operations from Tân Sơn Nhất to Long Thành airport, VnExpress reported. The airport in Đồng Nai is expected to open for commercial flights on 24 December.
According to the report, which cites a survey by the Civil Aviation Authority of Vietnam sent to government leaders, all international carriers back the move in principle because of the airport's modern infrastructure and capacity. The authority consulted airlines, IATA, industry associations, diplomatic bodies and domestic and foreign specialist agencies.
Of the 34, 24 airlines plan to operate at Long Thành from the winter 2027 schedule, which runs from late October to late March 2028. The other 10 propose the summer 2028 schedule, starting in late March, or later.
Airlines told the authority they need six to 12 months to plan route networks, aircraft and crew deployment, ground services and ticketing systems. Foreign aviation regulators may also need to inspect and approve safety conditions.
Cargo and transport demands
Logistics companies UPS, FedEx, DHL and Cargolux asked for an express cargo terminal, customs facilities, a truck-handling area and connecting transport links to be developed together. They said preparation and technical assessment could take about 12 months.
International airlines also asked for reliable transport links between Ho Chi Minh City and Long Thành, four-star transit hotels, high-quality medical services and a transition plan that treats domestic and foreign carriers fairly.
Domestic carriers ready
The Airports Corporation of Vietnam (ACV) plans up to 366 flights a week in the initial phase: 322 domestic and 44 international. Vietnam Airlines plans 72 flights a week and Vietjet up to 294, all domestic, and both say they are ready to operate from the start.
VnExpress notes that ACV's operational readiness programme has 55 scenarios in three phases between September and December 2026. The roughly three months between integrated trial operations in late September and the planned opening is much shorter than typical international practice, where major airports usually allow more time for testing and drills, the report said.
Phase one of the airport, on about 5,000 hectares, is designed for 25 million passengers and 1.2 million tonnes of cargo a year. International travellers using Da Nang should note that no change to the opening plan has been announced; the airlines' requests concern when they move, not whether.
Sources
This story was compiled by the Da Nang Voice news desk from the published sources listed above. Facts, figures and quotes are attributed to those sources; Da Nang Voice did not conduct interviews for it unless the text says so. Corrections are dated and noted at the top of the story. Read our corrections policy. Spotted an error? Tell us.