Asphalt for Long Thành International Airport is running short as bitumen imports from Singapore dry up, according to an Airports Corporation of Vietnam (ACV) progress report cited by Dân Trí on 12 November. Replacement supply from Malaysia and possibly China is scarce and costs more, the outlet reports.

The shortage hits Package 4.8, which covers the airport's ground transport and technical infrastructure and is worth more than 11,066 billion dong. The package needs about 355,130 tonnes of asphalt concrete, of which about 120,059 tonnes had been laid, leaving more than 235,000 tonnes.

Where the work stands

As of 2 November, asphalt on the main runway was about 36.44% complete and on service roads about 51.29%. The subgrade and crushed-stone base was over 86% done on the main road and over 96% on service roads.

ACV's targets are two-thirds of the asphalt layers from Gate 1 to the passenger terminal by the end of November. The remaining works, including the eastern section, sidewalks, greenery and road markings, are due by 24 December. ACV told contractors to fix the shortages so the airport is ready for operation in December.

A wider supply squeeze

The airport is not the only project affected. VietnamPlus reported on 10 November that bitumen is scarce and expensive across the road sector. Ministry of Construction figures cited there put the October average at about 26,689 dong per kilogram, up about 16.7% on September.

The report points to the Middle East conflict, higher crude prices, shipping costs and a high import exchange rate. On the Cam Lộ–La Sơn expressway expansion, suppliers said they would stop supplying Singapore-sourced bitumen in October because stocks had run out, and asphalt work there halted.

Other packages at risk

According to Dân Trí, ACV lists four packages that could delay the airport: 4.8, the passenger terminal (5.10), cargo terminal No. 1 (7.8) and the car park (11.5). Of the 16 construction packages in the airport's main contract, four are complete, eight are on track and four are at risk.

Overall, the work done had reached about 76,215 billion dong, or 87.83% of contract value, with about 49,042 billion dong disbursed, as of 2 November. The airport, with a planned capacity of 25 million passengers a year from its first terminal, is due to open in just over a month.

Sources

This story was compiled by the Da Nang Voice news desk from the published sources listed above. Facts, figures and quotes are attributed to those sources; Da Nang Voice did not conduct interviews for it unless the text says so. Corrections are dated and noted at the top of the story. Read our corrections policy. Spotted an error? Tell us.