Dong Nai's provincial Party leadership met Vietnam Airports Corporation (ACV) on 19 November to prepare for the planned commercial opening of Long Thành International Airport at 0:00 on 24 December 2026, according to a report reposted on the Civil Aviation Authority of Vietnam website from the Xây dựng newspaper.
ACV, which operates the airport, outlined a three-phase ramp-up. Phase 1 runs from 24 December to the end of March 2027, matching the 2026–2027 winter flight schedule. Phase 2 covers April to October 2027, and phase 3 begins from October 2027.
In phase 1 only the west runway area and the central area of Terminal T1 will open. Initial throughput is put at about 6–10 percent of design capacity, or 20–30 flights a day. The report says airlines have registered up to 366 flights a week, with priority for registered domestic and short-haul international routes.
ACV asked Dong Nai to help organise ground transport to and from the airport, support security, aviation safety, firefighting, search and rescue and airspace management, and provide health services, epidemic prevention and quarantine.
On roads, the report says component 1 of the Biên Hòa–Vũng Tàu expressway and component 3 of Ho Chi Minh City's Ring Road 3 are being accelerated, with completion targeted for December 2026. Roads 25B and 25C are to open in step with the airport. Dong Nai's Department of Construction has issued a plan to finish the connecting expressways and traffic arrangements.
Võ Tân Đức, deputy secretary of the Dong Nai Party Committee, said the project is entering a decisive stage and the aim is to open phase 1 in December 2026. "The time remaining is not much and the workload is very large," he said, in the report's account.
The province directed ACV to report its readiness and operating plans, define coordination with city and functional agencies and name a contact point for incidents. The Department of Construction was told to review roads 25B and 25C, the Ho Chi Minh City–Long Thành–Dầu Giây expressway, the Biên Hòa–Vũng Tàu expressway and the direct access roads with ACV.
The 24 December date is a plan. Other recent reports have noted that some international airlines have asked for a later move.
Sources
This story was compiled by the Da Nang Voice news desk from the published sources listed above. Facts, figures and quotes are attributed to those sources; Da Nang Voice did not conduct interviews for it unless the text says so. Corrections are dated and noted at the top of the story. Read our corrections policy. Spotted an error? Tell us.