The Ministry of Construction has set a string of November deadlines for getting phase 1 of Long Thành International Airport ready to open, with the airport's operator due to report on 15 November, according to Thanh Niên and Dân Trí on 10 November.
Both outlets say the ministry sent the instruction to the Civil Aviation Authority of Vietnam (CAAV) and the Airports Corporation of Vietnam (ACV). It follows a directive from Deputy Prime Minister Permanent Phạm Gia Túc in Government Office Document No. 11272, dated 5 November, which called for faster progress on phase 1.
The deadlines
ACV must review progress on its contract packages, works and the ORAT trial-operation programme, and line up construction completion, acceptance, legal procedures and aviation licensing with actual operations. It is also to draft an operating plan with CAAV and other agencies, with security, safety and feasibility named as the priorities. Its report is due on 15 November.
CAAV, which acts as the standing body of the steering committee for the airport, must review ACV's operating plan and send its findings to the ministry by 18 November. The ministry will then hold a meeting in November to review preparations.
Roads to the airport
Two ministry departments, the Department of Construction Economics and Management and the Vietnam Road Administration, must check the expressways and national and provincial roads linked to the airport. Their report on connectivity is due on 16 November. The stated aim is to avoid congestion when the airport opens.
The opening date
Dân Trí reports that ACV has told CAAV phase 1 is planned to open from 00:00 on 24 December, and that ACV has asked airlines to prepare their own operating plans. Thanh Niên reports the ministry's requirement that the phase be ready for operation by 31 December.
Dân Trí also notes that CAAV recently called an investor proposal to delay part of the project to 2027 "without basis".
Sources
- Bộ Xây dựng ra 'deadline' báo cáo đầu việc chuẩn bị khai thác sân bay Long Thành
- Bộ Xây dựng chốt thời hạn rà soát điều kiện khai thác sân bay Long Thành
This story was compiled by the Da Nang Voice news desk from the published sources listed above. Facts, figures and quotes are attributed to those sources; Da Nang Voice did not conduct interviews for it unless the text says so. Corrections are dated and noted at the top of the story. Read our corrections policy. Spotted an error? Tell us.