Construction of Terminal T2 at Phu Quoc International Airport, built for the APEC 2027 summit, is advancing on its roof and baggage systems, Tuoi Tre reported on 19 November. The building, known as the "Phoenix wing", is in An Giang province and is designed to handle 20 to 24 million passengers.

According to the report, the steel frame of the main roof is finished on one side. Contractors are laying roofing, fitting glass to the front and rear faces and installing baggage conveyors. The terminal is to have a highly automated baggage-handling system.

Thousands of engineers and workers are on site, the report says, with more than 1,000 inside the terminal. One representative said up to 800 are working on water supply and drainage, lighting and fire protection.

Nguyen Van Hoang of contractor Thai Yen said the airport access bridge has reached 70 to 80 percent of its volume of work. Nguyen Duong Duc Anh of mechanical and refrigeration engineering company REE said, "We are speeding up to finish on schedule." Sun Group said the builders are accelerating the work.

The investor expects to finish the terminal before APEC 2027. The report gives no opening date for flights and no total investment figure, and Danang Voice has not independently verified the progress described.

Sources

This story was compiled by the Da Nang Voice news desk from the published sources listed above. Facts, figures and quotes are attributed to those sources; Da Nang Voice did not conduct interviews for it unless the text says so. Corrections are dated and noted at the top of the story. Read our corrections policy. Spotted an error? Tell us.