About 1,200 to 1,300 engineers and workers are building the 17.59 km light rail line on Phú Quốc island, working through a late-October heat wave, according to Thanh Niên.

The line will link Phú Quốc airport with the south of the island, where venues for the APEC 2027 summit and tourist sites are located. Total investment is about 9,000 billion dong under a build-operate-transfer model, with 70 percent from the state and 30 percent from Sun Group.

Thanh Niên reported that crews are working across seven fronts. By the end of October more than 11 km of single track had been laid, out of roughly 35 km in total. All bored piles for tunnels and bridges are finished, and station structures are under construction alongside the track work.

Design speed is 70 to 100 km/h, with capacity of about 4,500 passengers an hour and an end-to-end journey of around 20 minutes. The initial fleet is planned at six to ten three-car trains running on clean energy, rising to as many as 14 trainsets, with its own depot. Road crossings are to be handled by bridges and tunnels to minimise level crossings.

Officials have committed to finishing all APEC-related projects before 30 June 2027. At a 25 October working session with a delegation led by National Assembly Chairman Trần Thanh Mẫn, An Giang provincial chairman Hồ Văn Mừng said the projects were on schedule, the paper reported.

Sources

This story was compiled by the Da Nang Voice news desk from the published sources listed above. Facts, figures and quotes are attributed to those sources; Da Nang Voice did not conduct interviews for it unless the text says so. Corrections are dated and noted at the top of the story. Read our corrections policy. Spotted an error? Tell us.