The Phuoc An Bridge across the Thi Vai River, a nearly VND 5 trillion link to the Cai Mep port cluster, is targeted for completion in 2027, according to Dan Tri. The report cites the Management Board of Transport Infrastructure Projects of Ho Chi Minh City.
The bridge connects Phu My ward in Ho Chi Minh City with Phuoc An commune in Dong Nai. It links the Ben Luc - Long Thanh expressway with the Cai Mep - Thi Vai ports and Phuoc An port. The full route is about 4,378 metres, including a 3,514-metre bridge section.
The main span is 250 metres in an extradosed design, described in the report as the longest of its type in Southeast Asia. Navigation clearance is 55 metres, the same as the Phuoc Khanh Bridge, and the bridge will have six lanes.
Construction started more than three years ago. The main spans were joined in late July, and cable stays at piers T38 and T39 are complete.
The investor has asked contractors to speed up work in the last two months of the year, finishing packages 38 and 39 and accelerating packages 40 and 41. An elevated access road of about 617 metres to Phuoc An port, running over mangrove forest, is about 70 percent complete.
The board expects shorter travel times, less pressure on National Highway 51 and an extra freight route for eastern Ho Chi Minh City and Dong Nai.
Under the plan described in the report, vehicles from the Hoi Bai - Chau Pha interchange on the Bien Hoa - Vung Tau expressway could reach the bridge directly. The investor says the remaining work depends on the last two months of the year; the 2027 target is a stated plan, not a confirmed opening date.
Sources
This story was compiled by the Da Nang Voice news desk from the published sources listed above. Facts, figures and quotes are attributed to those sources; Da Nang Voice did not conduct interviews for it unless the text says so. Corrections are dated and noted at the top of the story. Read our corrections policy. Spotted an error? Tell us.