Quang Tri's government has told a toll-road investor to hand over land for two highway interchanges before 1 December, after a dispute over lost toll revenue stalled the connections.

According to Tuoi Tre, the provincial People's Committee office issued a conclusion from chairman Bui Hoang Phuong on 27 November. It covers two new roads that must join National Highway 1 within projects worth VND250 billion.

The investor is Truong Thinh Group, which holds two build-operate-transfer projects: the Highway 1 bypass of Dong Hoi and the bypass of the former Quang Ninh and Le Thuy districts. The main obstacle is the investor's concern about losing toll revenue, which is why it has not agreed to the connections.

The first interchange links Dien Bien Phu road with the Dong Hoi bypass. The 1.4-kilometre, 36-metre-wide road was finished in mid-2023, but traffic from Nhat Le 2 Bridge still cannot reach the bypass.

It was funded with VND165 billion of World Bank capital.

Work resumed in early 2026 with more than VND20 billion, and the contractor entered the site in March. In late May, the investor reported to provincial and ward police that slope removal was damaging the road structure, and work stopped.

The second is Dinh Muoi road, more than 4 kilometres long, passing Ninh Chau and Quang Ninh communes. It costs VND91 billion and is funded by an Asian Development Bank loan, with completion expected at the end of December.

The Quang Binh Comprehensive Infrastructure Development Project Management Board said that if the road cannot connect to the toll road, the bank may cancel the loan in 2026. The project could then miss acceptance and payment deadlines.

For a third road, to the Le Duan Memorial Area, the investor must hand over the site immediately after receiving a construction permit.

Truong Thinh must urgently review why revenue might fall and submit a full dossier to the Vietnam Road Administration before 1 December. The administration, which signed the contract, is asked to guide and coordinate.

The province says toll losses caused by local roads will be handled under the law and the contract, and it will work with the Ministry of Construction on a financial adjustment plan.

Source: Tuoi Tre

Sources

This story was compiled by the Da Nang Voice news desk from the published sources listed above. Facts, figures and quotes are attributed to those sources; Da Nang Voice did not conduct interviews for it unless the text says so. Corrections are dated and noted at the top of the story. Read our corrections policy. Spotted an error? Tell us.