Ho Chi Minh City's approved master plan keeps Tan Son Nhat airport as a major international hub rather than moving all scheduled foreign flights to Long Thanh.

According to Dan Tri, the plan, which looks 100 years ahead, treats Tan Son Nhat as one of the country's two largest international transit hubs through 2050.

The airport is classed as Code 4E, with a design capacity of about 50 million passengers a year by 2030. The consultant preparing its planning file, ADCC, says the airport will receive more infrastructure for both international and domestic traffic.

Planned work includes better ground links to the city, an upgraded older runway and a renovated Terminal 1. The plan also lists better connections between terminals, new equipment and new air traffic control systems.

Tan Son Nhat has one pair of dependent parallel runways that sit too close together to operate independently. ADCC says many countries handle around 50 million passengers a year with such a layout.

The consultant argues that the main constraint is road and transit access rather than runway capacity. Airports handling 30 million or more passengers a year are required to have an urban rail connection.

ADCC says the two airports will operate in parallel, with Long Thanh in Dong Nai mainly serving long-haul international routes. The plan gives Long Thanh a first-stage capacity of about 25 million passengers a year and roughly 100 million by 2035.

The outcome differs from options floated at a September 2025 seminar organised by the Aviation Academy. Consultants from South Korea's Incheon Airport presented one option to move all international flights and 5 percent of domestic flights to Long Thanh, and another to move 80 percent of international flights while keeping short-haul routes under 1,000 kilometres at Tan Son Nhat.

Incheon pointed to South Korea's move of all international flights from Gimpo to Incheon. Other voices urged caution: architect Ngo Viet Nam Son proposed a three-stage approach, and the International Air Transport Association said keeping both airports is unavoidable if Long Thanh cannot handle all of the city's traffic.

For Terminal 1, ADCC and CPG propose a high-rise building with capacity of 10 million passengers a year, expandable to 15 million. The design adds a VIP terminal and a service complex.

Terminals would connect to the city metro through escalators, walkways and elevated bridges. Two metro stations are planned at Tan Son Nhat, one linked to Terminal 3 and one between Terminals 1 and 2.

The article also notes related developments. ACV has proposed delaying completion of Long Thanh's first stage to 2027-2028, and the Civil Aviation Authority has urged the city and Dong Nai to finish connecting roads.

A dedicated 24-hour shuttle on the expressway between the two airports has been proposed. A second calibration flight at Long Thanh is expected in early December 2026.

Source: Dan Tri

Sources

This story was compiled by the Da Nang Voice news desk from the published sources listed above. Facts, figures and quotes are attributed to those sources; Da Nang Voice did not conduct interviews for it unless the text says so. Corrections are dated and noted at the top of the story. Read our corrections policy. Spotted an error? Tell us.