Widening of the Ho Chi Minh City to Long Thanh expressway is about 80 percent complete on its largest package, according to a progress report from VOV on 14 November. The project is meant to ease congestion on the route to the new Long Thanh international airport.

Nguyen Ngoc Lam, director of package XL01, said the contractor joint venture led by Deo Ca Group has nearly 900 people, more than 200 machines and 33 work fronts on site. Package XL01 is nearly 10 kilometres long and worth nearly VND 5.6 trillion.

Girder erection stands at 92 percent, first-stage deck slabs at 81 percent and railings at 43 percent. Bored piles for the elevated sections are finished and the substructure is about 98 percent done.

Work began in August 2025, but the full site was handed over only in June 2026, which shortened the schedule. The elevated sections and the Song Tac bridge are due in November so traffic can be diverted while the old deck is repaired.

The Long Thanh main bridge, about 2.3 kilometres long and 23.75 metres wide, is the biggest component. Cantilever casting has reached 8 of 85 segments, with closure targeted for late December 2026 and the package due for completion in March 2027.

The existing 55-kilometre expressway opened in 2015 at a cost of VND 20.6 trillion. Once widened to 8-10 lanes it is meant to reduce congestion, especially on weekends and holidays.

The report links the delays to the late site handover and says further slippage would affect the wider economy of the southeast region. It does not name a government agency or project management board, so the progress figures come from the contractor side.

Sources

This story was compiled by the Da Nang Voice news desk from the published sources listed above. Facts, figures and quotes are attributed to those sources; Da Nang Voice did not conduct interviews for it unless the text says so. Corrections are dated and noted at the top of the story. Read our corrections policy. Spotted an error? Tell us.