The Tuy Loan interchange in western Da Nang is 65 percent complete, and the city has ordered its 1.6-kilometre connecting road opened by 31 December.

According to VietnamPlus, the interchange links National Highway 14B with the Da Nang–Quang Ngai expressway at the city's western gateway. The special-grade project has a total investment of VND537.637 billion on a planned area of 32.4 hectares.

Construction began in late 2025. After more than 11 months, the National Highway 14B overpass was completed and opened to traffic.

Before that, vehicles had to stop at a signal-controlled level crossing with the highway.

The overpass has 14 of 14 pier abutments finished and all 72 Super T girders lifted into place. Crews have installed 442 metres of railing and laid 6,251 square metres of asphalt on the deck.

On the main alignment, 16 of 16 slab girders and 20 of 20 culverts are done.

Consultant supervisor Nguyen Dang Tan said the overpass separates traffic levels and allows a through route between the two expressways. The 1.6-kilometre central connecting road must meet expressway load-bearing standards, with compacted subgrade, aggregate and cement-stabilised bases and several asphalt layers.

Because heavy traffic still passes through the site, the contractor builds the road in sections of 200 to 300 metres. Each lane is finished before traffic is switched to it.

Construction commander Nguyen Xuan Gioi said the work had to balance technical requirements, safety and appearance.

Crews work three shifts with four teams each and use the few dry days of the central region's rainy season. As of mid-November, 100 percent of the allocated capital, VND295.745 billion, had been disbursed.

Three land-clearance files remain unresolved. They concern a village temple in Ba Na commune, Petrolimex petrol station No.

21, and land linked to the Mobile Police Command on frontage road No. 1.

Work on the connecting ramps and surrounding traffic areas is being sped up with more machinery and workers. VietnamPlus says that once the three sites are handed over and the ramps are finished, the project should remove the bottleneck on the North–South expressway through Da Nang ahead of 5 June 2027.

Source: VietnamPlus

Sources

This story was compiled by the Da Nang Voice news desk from the published sources listed above. Facts, figures and quotes are attributed to those sources; Da Nang Voice did not conduct interviews for it unless the text says so. Corrections are dated and noted at the top of the story. Read our corrections policy. Spotted an error? Tell us.