Vietnam's power projects need nearly US$135 billion through 2030, and Tuoi Tre reports that attracting private capital is proving difficult.

According to Tuoi Tre, the national power transmission corporation EVNNPT must arrange financing for about 220 projects. That excludes ultra-high-voltage direct current lines and projects to carry nuclear power.

Loan demand is about VND204 trillion, or US$7.8 billion, based on the approved Power Master Plan VIII.

The article cites about US$114 billion needed for generation sources alone through 2030. EVNNPT has repeatedly invited domestic and foreign credit institutions to arrange capital, and the Vietnam Development Bank is a source of preferential loans.

Domestic loans are quicker to appraise and sign, but single-borrower credit limits under the Law on Credit Institutions have been lowered step by step. Foreign loans are larger, with longer maturities and grace periods, but carry stricter environmental and social requirements and slower appraisal.

The Ministry of Industry and Trade says private investment in power projects, especially transmission grids, faces difficulties. Barriers include unclear transmission pricing, incomplete risk-sharing and revenue guarantees, and complicated procedures for land and investor selection.

For renewables and LNG, pricing and procedures for wind and solar, including offshore wind, are still being finalised. Investors therefore face long waits, the article says.

Dang Quoc Bao, deputy general director of Trungnam Group, said the company, which has invested in LNG, solar and wind projects, will work directly with authorities to resolve obstacles. Somsak Chutanan, an adviser to Gulf Energy, proposed an LNG hub including a terminal at Hon Me–Nghi Son and a 4,500-megawatt plant.

He said lenders need stable cash flow from reliable long-term gas demand and service contracts.

The recommendations include better power purchase agreements, electricity prices that reflect actual costs under government oversight, and upgraded transmission. They also call for a stable long-term policy framework and faster inter-agency coordination.

Tuoi Tre notes that very few major projects in Power Master Plan VIII have started construction, which raises concern about supply in 2027 and from 2028 to 2030. An earlier article in the series reported that only about 5 percent of projects have entered operation.

Source: Tuoi Tre

Sources

This story was compiled by the Da Nang Voice news desk from the published sources listed above. Facts, figures and quotes are attributed to those sources; Da Nang Voice did not conduct interviews for it unless the text says so. Corrections are dated and noted at the top of the story. Read our corrections policy. Spotted an error? Tell us.