Da Nang officials have ordered faster work on the National Route 14D upgrade, aiming to finish the first 10.2 kilometres before the 2027 Lunar New Year.

The city government portal danang.gov.vn reported that Deputy Chairman of the Da Nang People's Committee Tran Nam Hung chaired a working session on the project on 23 November.

The investor is the Da Nang Project Management Board for Transport and Agriculture Construction. Contractors, the city's Land Development Fund Development Center and the communes of Ben Giang, Nam Giang and La Dee took part.

The project upgrades a 65.37-kilometre route at a total investment of 4,518 billion dong. Construction began on 26 June 2026, and full completion is expected in 2028.

The immediate target is to complete the section from Km0 to Km10+200, including two asphalt layers, before Tet in 2027. The portal gave no progress percentages.

Contractors are mobilising labour, machinery and equipment, but only at locations where the site has been cleared. Work covers subgrade, pavement foundations, bridges, culverts, drainage and retaining walls.

Some sections have completed graded crushed-stone base layers and asphalt surfacing. On bridges, crews are boring piles and building piers, abutments and beams, and contractors are precasting culvert units and bridge beams for later sections.

Site clearance is the main brake. Of 2,585 affected land plots along the route, 1,947 dossiers have been surveyed and 1,887 sent to the communes for verification of land origin and legal status.

The communes have confirmed and returned 1,047 dossiers, and 331 have completed price appraisal and public posting. Compensation plans have been approved for 121 cases, and in 88 cases payment has been received and the site handed over.

Other problems include relocating medium- and low-voltage power lines and transformer stations, procedures for converting forest land to other uses, and the supply of construction materials. These issues affect the ability to organise work, complete volumes and disburse funds according to the 2026 plan.

Hung directed the management board and the Land Development Fund center to second staff to help the communes speed up compensation, resettlement and handover paperwork. Contractors were told to work wherever sites are ready and to follow item-specific schedules.

Quality, labour safety and traffic management along the whole route must be maintained, with minimal disruption to residents. The route, which serves the mountain communes of western Da Nang, was the subject of earlier decisions on heavy-truck access.

Sources

This story was compiled by the Da Nang Voice news desk from the published sources listed above. Facts, figures and quotes are attributed to those sources; Da Nang Voice did not conduct interviews for it unless the text says so. Corrections are dated and noted at the top of the story. Read our corrections policy. Spotted an error? Tell us.