Dong Nai city has approved an investment of more than 9,000 billion dong for the road linking the future Cat Lai Bridge to the Ben Luc - Long Thanh Expressway.
Dan Tri reports that the Dong Nai City People's Committee approved the first component project of the Cat Lai Bridge scheme on 23 November.
The component covers compensation, site clearance and construction of the connecting road and bridges from the Dong Nai-side approach of the bridge to the expressway. Of the total, more than 4,300 billion dong is for site clearance and more than 3,600 billion dong for roads and bridges, with the rest going to other costs.
The connecting road is nearly 8 kilometres long and includes six bridges. It is designed to urban main trunk road standards with a design speed of 80 kilometres an hour.
In the first phase it will have parallel carriageways with three lanes on each side and a roadbed 13.25 metres wide. The road will have a grade-separated interchange with the expressway, plus interchanges with Lien Cang Road, Road 25C and local roads.
A five-lane non-stop toll station is planned before the expressway at about Km12+600. It will be combined with vehicle weight control and an intelligent transport system.
Land clearance is based on a complete right-of-way plan 100 metres wide, covering the whole Cat Lai Bridge project area and the connecting road in Dong Nai. The land required totals nearly 126 hectares.
The work is to be funded from the Dong Nai city budget over 2026 to 2029. The plan sets aside 64.8 billion dong from 2026, with further allocations according to progress, and the Dong Nai Traffic Infrastructure Project Management Board is the investor.
The bridge itself, according to the paper, broke ground in late September. The whole project is more than 11.6 kilometres long, including a main bridge and approach bridges totalling 3.65 kilometres.
It runs from the My Thuy interchange on Ring Road 2 in Cat Lai ward, Ho Chi Minh City, across the Dong Nai River to the expressway in Dai Phuoc commune. The cross-section has six motor lanes and two non-motorised lanes, with the same 80 kilometre an hour design speed.
The main bridge is cable-stayed with two cable planes, a main span of 450 metres and a navigation clearance of 55 metres. That clearance allows container ships of up to 60,000 deadweight tonnes to pass beneath.
Dan Tri's related coverage notes that the total investment in the Cat Lai Bridge project has risen from more than 20,600 billion dong to more than 24,000 billion dong, an increase of nearly 3,500 billion dong. Compensation and resettlement costs account for about 1,500 billion dong of that rise.
Sources
This story was compiled by the Da Nang Voice news desk from the published sources listed above. Facts, figures and quotes are attributed to those sources; Da Nang Voice did not conduct interviews for it unless the text says so. Corrections are dated and noted at the top of the story. Read our corrections policy. Spotted an error? Tell us.