The main structures of Gia Binh International Airport have taken shape after 15 months of construction, with the control tower topped out and runway ground work nearly done.

According to Dan Tri, thousands of workers and hundreds of tonnes of machinery are on site in three shifts across four crews.

Construction began on 19 August 2025. The target opening is February 2027, in time for the APEC Economic Leaders' Meeting.

The airport is planned as a dual-use civil and military facility covering about 1,960 hectares, with two runways of 3,500 to 4,000 metres each. It lies about 40 kilometres from central Hanoi, close to industrial parks in Bac Ninh, Hung Yen and Hai Phong.

The capacity targets are 30 million passengers and 1.6 million tonnes of cargo a year by 2030. By 2050 those rise to 50 million passengers and 2.5 million tonnes.

On the runway, ground reinforcement with cement-deep-mixing piles is 99.6 percent complete and sand filling is 91 percent done. The graded aggregate base is 82.2 percent complete.

On the apron, pile reinforcement is 89.9 percent complete and sand filling 79.6 percent. Graded aggregate stands at 14.2 percent, lean concrete at 6.6 percent and surface concrete at 2.1 percent.

Across the airfield, lean concrete is 73.5 percent complete and pavement concrete 58.8 percent. Lighting work is under way, with concrete poured for main cable ducts, conduits laid and light holes being drilled.

The air traffic control tower topped out in June 2026. Its steel structure for floors one to 19 is about 40 percent complete, and the cabin steel from floor 21 to the roof is 36 percent done.

Wall construction and mechanical and electrical installation have started, and the facade is being prepared.

The VIP terminal in the south has part of its curved steel roof in place. About 168 workers are plastering and installing mechanical and electrical systems in the basement.

At navigation station A-08, the foundation and structure are finished and the DVOR/DME system is installed. The first calibration flight was scheduled for 24 and 25 November.

A northwest passenger terminal and a southwest cargo terminal are planned for later phases.

Source: Dan Tri

Sources

This story was compiled by the Da Nang Voice news desk from the published sources listed above. Facts, figures and quotes are attributed to those sources; Da Nang Voice did not conduct interviews for it unless the text says so. Corrections are dated and noted at the top of the story. Read our corrections policy. Spotted an error? Tell us.