Hai Phong is attaching QR codes to each public project and building an automatic alert system to flag those falling behind schedule, as the port city pushes to disburse all of its 2026 public investment capital.
Thanh Nien reports that Vice Chairman Le Trung Kien has told the Department of Science and Technology to upgrade the city's Intelligent Operation and Monitoring Center urgently and to update the project list. The alerts are meant to help city leaders spot problems early and direct efforts to remove obstacles.
As of 15 November, Hai Phong had disbursed more than 36.479 trillion dong in total. Of that, 35.943 trillion dong came from the 2026 plan capital, or 93 percent of the target set by the Prime Minister.
Of 125 investors and localities, 47 have disbursement rates below 86 percent. That is the group the city will be pressing hardest in the final weeks of the year.
Site clearance remains the main obstacle. Of 221 public investment projects due for completion in 2026, 66 have not finished clearing land.
Progress stands at 75.8 percent for the Lao Cai to Hanoi to Hai Phong railway and 76.3 percent for the Hanoi to Quang Ninh high-speed railway. Localities are told to resolve the obstacles and avoid carrying them into 2027.
The Department of Finance, led by Director Nguyen Ngoc Tu, will track actual progress and propose moving capital between projects. The targets are to finish disbursing the capital allocated at the start of the year before 30 November and to disburse supplementary capital in December.
Disbursement results will be the basis for rating each unit's year-end performance. Moving money from slow projects to faster ones is a common practice in Vietnam, but it depends on projects being ready to absorb it.
The report does not say how the QR codes will be displayed to the public or what information they will show. It also does not say when the alert system will go live.
The same pressure to spend is being felt elsewhere. Da Nang reported earlier this week that its own 2026 public investment disbursement stood at 78 percent.
Source: Thanh Nien
Sources
This story was compiled by the Da Nang Voice news desk from the published sources listed above. Facts, figures and quotes are attributed to those sources; Da Nang Voice did not conduct interviews for it unless the text says so. Corrections are dated and noted at the top of the story. Read our corrections policy. Spotted an error? Tell us.