Ho Chi Minh City has issued a land recovery plan to widen Vinh Loc Road over more than 7.1 kilometres, with all site handover targeted for 31 March 2027. According to Thanh Nien, the project's total investment has been raised to VND6.871 trillion from the earlier VND807 billion.
The plan covers compensation, support, resettlement and land recovery for the section from Tran Van Giau Road to Road No. 2A in the Vinh Loc industrial park. It sets out 16 steps, from planning and recovery notices to surveys, property counts, checks on land origin and approval of compensation plans.
The city wants all payments, land recovery and handover completed by 31 March 2027. Units must carry out eligible tasks at the same time instead of waiting for each step to finish.
Public and lawful process
The plan says the process must be public, transparent and lawful, and must protect the legitimate rights of affected people. It calls for outreach and dialogue.
Where residents disagree with a compensation plan or do not cooperate, officials must explain the policy and handle complaints. If people still do not hand over land, authorities will keep persuading them.
Forced enforcement of the recovery decision may be considered only as a last step, when every legal condition and procedure has been met.
Scope and budget
The city People's Council approved the adjustment that lifted investment to VND6.871 trillion. The road will be widened to 30 metres and passes through Binh Loi, Vinh Loc and Tan Vinh Loc communes and Binh Tan ward.
Works include the Ba Tri bridge at 31 metres wide, a larger Vinh Loc and Tran Van Giau intersection and added right-turn access points. The Vinh Loc five-way intersection, where Vinh Loc, Quach Dieu, Vo Van Van and Nguyen Thi Tu roads meet, will be built to plan with traffic organised at grade.
The project has two components. Compensation, support and resettlement account for about VND5.807 trillion, and the road upgrade and widening for about VND1.064 trillion.
Timeline
The Tan Nhut commune Project Management Board is the investor for both components. After site clearance it will select contractors, and the project is expected to open in the third quarter of 2028.
Photographs with the report show the current road is narrow, with one lane in each direction, and that many sections have no drainage system.
Source: Thanh Nien
Sources
This story was compiled by the Da Nang Voice news desk from the published sources listed above. Facts, figures and quotes are attributed to those sources; Da Nang Voice did not conduct interviews for it unless the text says so. Corrections are dated and noted at the top of the story. Read our corrections policy. Spotted an error? Tell us.