The company building Long Thanh International Airport has asked the government to extend the first-phase deadline to 2027 or 2028, saying parts of the project cannot be finished this year.

VnExpress International reports that the Airports Corporation of Vietnam (ACV) made the request at a meeting with Standing Deputy Prime Minister Pham Gia Tuc on Wednesday. The airport is in Dong Nai province, about 40 km east of Tan Son Nhat.

The third component, which covers essential airport facilities, is 88.6 percent complete, and disbursements have reached 57 percent of the contract value. ACV said it cannot finish the whole component by this year's contractual deadline.

Construction or test runs under several major contracts are expected to wrap up in June 2027. These include the passenger terminal, the first cargo terminal, the car park building and the airport management system.

ACV listed three obstacles it says must be resolved before works can be formally accepted and the airport licensed to operate. Some materials and equipment differ from contract specifications in manufacturer, brand, type or origin, and were ordered and installed before the changes were approved and contracts amended.

Some facilities were also built and accepted on construction drawings that differ from the approved technical designs, which have not yet been amended. Others were built before their drawings were approved.

In late October, ACV had expected operations to begin at midnight at the start of 24 December, initially handling a maximum of about 366 flights a week. The report says the project cannot be completed in 2026 as approved by the National Assembly.

Deputy Minister of Construction Pham Minh Ha asked ACV to review the changes made during construction. For equipment that does not match the specifications, he called for a review of value and cost, quality testing and an assessment of technical compliance, with ACV responsible for arranging the tests.

Deputy Minister of Justice Nguyen Thanh Tu asked ACV to say when it could complete the project. Nguyen Cong Long, general director of the Vietnam Air Traffic Management Corporation, said remaining work on the second component depends on infrastructure in the third.

Tuc directed ACV to review all remaining work and set clear dates for construction, equipment installation, test runs, trial operations and entry into service. ACV must report to the government and the Ministry of Construction within a week of the meeting.

Before 10 December, the Ministry of Construction must report progress to the government so authorities can decide whether to amend the investment policy. Tuc told ACV to press contractors to mobilise all available workers, machinery and funds, add shifts and overtime, and to report contractors that miss their obligations.

ACV must also announce a start date for operations and, once it receives official notice, tell airlines so they can plan flights. The project costs nearly US$16 billion across three phases, and the first phase is designed for 25 million passengers and 1.2 million tonnes of cargo a year.

Source: VnExpress International

Sources

This story was compiled by the Da Nang Voice news desk from the published sources listed above. Facts, figures and quotes are attributed to those sources; Da Nang Voice did not conduct interviews for it unless the text says so. Corrections are dated and noted at the top of the story. Read our corrections policy. Spotted an error? Tell us.