Authorities have agreed a plan that splits road access to Long Thanh International Airport into three main directions ahead of its planned opening.
According to Thanh Nien, the Vietnam Road Administration sent the plan to the Ministry of Construction in a report on connecting the Bien Hoa to Vung Tau expressway and other roads to the airport.
Travellers from central Ho Chi Minh City and the Mekong Delta have three routes. They can take the Ho Chi Minh City to Long Thanh to Dau Giay expressway, exit at Long Thanh and join Component 2 of the Bien Hoa to Vung Tau expressway.
Others can use the Ben Luc to Long Thanh expressway and exit at Tan Hiep, or drive from Thu Duc through Ring Road 3, the Nhon Trach Bridge, provincial road DT.25C and road T1.
From the former Ba Ria to Vung Tau area, drivers will use Component 3, switch to Component 2 and reach road T1. They can also take National Highway 51 through DT.25C.
From Dong Nai city and the northern provinces, the route is Components 1 and 2 and then Highway 51 through DT.25C, while vehicles from Lam Dong can use the Dau Giay expressway and turn onto Component 2.
Localities will also run public bus networks that link directly to the airport. The report asks that coaches and trucks serving airport operations be added to the overall traffic plan.
All three components of the Bien Hoa to Vung Tau expressway currently allow vehicles under nine seats. Component 1 is repairing some sections, with completion targeted for 31 December.
Component 2, with a maximum speed of 80 kilometres an hour, is expected to approve a supplementary traffic plan at the Tan Hiep interchange in early December, allowing it to connect with the Ben Luc to Long Thanh expressway.
Roads T1 and T2, which connect directly to the airport, are complete and ready, and toll stations are being installed. Repairs to the Highway 51 surface are expected to finish on 20 December.
Ring Road 3 packages in Ho Chi Minh City will be completed within 2026.
The administration asked the ministry to push Project Management Board 85, the Vietnam Expressway Corporation and the Vietnam Airports Corporation to finish remaining work quickly. It also asked for the agencies to agree on a maximum operating speed.
The report notes that Long Thanh is expected to handle 30 to 40 flights a day during Tet 2027. About 10 kilometres of the Ho Chi Minh City to Long Thanh to Dau Giay expressway were widened to 10 lanes, with traffic moved to the new lanes from 22 November.
Source: Thanh Nien
Sources
This story was compiled by the Da Nang Voice news desk from the published sources listed above. Facts, figures and quotes are attributed to those sources; Da Nang Voice did not conduct interviews for it unless the text says so. Corrections are dated and noted at the top of the story. Read our corrections policy. Spotted an error? Tell us.